image-faceit

Faceit

Project Brief

Client

  • Faceit

Timescale

  • 4 weeks

Sector

  • Office

Surface

  • 6,000 sqft

Client Brief

FACEIT is the leading independent competitive gaming platform for online multiplayer PvP gamers

with more than eight million users, and a total of twelve million online gaming sessions each month. They aim to further the esports ecosystem by offering players of all levels the chance to compete in a competitive environment with the games they love while providing publishers and third party organisers with the tools needed to build their competitive community.

The FACEIT team developed their own proprietary platform that integrates the world’s leading competitive games and helps each publisher and organiser build a strong competitive community.

Throughout the project we encounter several challenges, such as distributing the power and Data to the centre of the meeting rooms

THE PROJECT

Lopez Landa Interiors was appointed to carry out the complete Cat B fit out project for Face IT

at their brand new offices in the Millbank Tower.

The first stage of this project consisted in a series of meetings and site visits to gain a better understanding of Faceit’s requirements and needs, to then translate this into the final space planning, achieving a main office area conformed in an open plan lay out, completed with two offices, various meeting rooms and a gaming room.

The office, located on the 25th floor of this tower, provided a superb panoramic view of London, creating a perfect environment full of natural light throughout the entire floor.

THE PROJECT

Lopez Landa Interiors was appointed to carry out the complete Cat B fit out project for Face IT

at their brand new offices in the Millbank Tower.

The first stage of this project consisted in a series of meetings and site visits to gain a better understanding of Faceit’s requirements and needs, to then translate this into the final space planning, achieving a main office area conformed in an open plan lay out, completed with two offices, various meeting rooms and a gaming room.

The office, located on the 25th floor of this tower, provided a superb panoramic view of London, creating a perfect environment full of natural light throughout the entire floor.

One of the keys in this projects was to re-use as much of the existing services as possible,

including the lighting, power, Air conditioning and Fire Alarm, which were initially distributed to suit the open plan of the space distribution.

The second most important element was the Data installation. The space had all the Data installation in place, however this had to be terminated and removed due to Faceits requirements for Cat6a cabling throughout.

The gaming room was the space that underwent the greatest change, as the client was looking for a more industrial look. To achieve this, we removed the entire suspended ceiling, leaving all services and the concrete and potted ceiling in view. This got fully decorated and a set of dimmable slimline LED panels was installed suspended from the soffit.
Throughout the project we encounter several challenges, such as distributing the power and Data to the centre of the meeting rooms, as we could not chase out the existing concrete floors but our technical department overcame this problem by installing a flooring grade plywood sheet over the floor, fully fixed to the stuctural floor and feathered a ramp to absorve the difference in level.

THE PROJECT

To complete this turnkey project, we supplied brand new furniture,

matching their existing benches and assisted Face IT with the full relocation of their office over a weekend, disconnecting all their systems on a Friday and getting the space operational by Monday morning, so their team could set their system immediately.

We thoroughly enjoyed working with Faceit in this project, helping such a great company to create their new office space and wish them every sucess.

“Many thanks for all your hard work -I think I express the opinion of the team and myself when I say we are very impressed. You have been courteous throughout and kept us informed of any issues/changes we realle appreciate”

THE PROJECT

To complete this turnkey project, we supplied brand new furniture,

matching their existing benches and assisted Face IT with the full relocation of their office over a weekend, disconnecting all their systems on a Friday and getting the space operational by Monday morning, so their team could set their system immediately.

We thoroughly enjoyed working with Faceit in this project, helping such a great company to create their new office space and wish them every sucess.

“Many thanks for all your hard work -I think I express the opinion of the team and myself when I say we are very impressed. You have been courteous throughout and kept us informed of any issues/changes we realle appreciate”

Case studies

View all
image-miniclip-london

Miniclip London

image-dandara-eastern

Dandara Eastern

Case studies

View all
image-tax&advice

Tax&Advice

image-miniclip-london

Miniclip London